Read more about the 2008 treatment
program.
Current Pond Conditions and Treatment Program
News
Update 7/31/08
From Mike Lowery of WSQC:
Dudley Pond was treated today with fluridone (liquid Sonar AS) in order to
bring concentrations back to 12ppb. Dosage was based on FasTEST samples taken
last week indicating concentrations near 7ppb, and now assumed to be about
6ppb. As before, dosage calculations were done separately by the four 'basins'
in FasTEST sampling.
Gerry (ftom ACT) said that in prior years, had he observed the plants in their current
state, ACT probably would not have done a booster treatment. WSWQC's treatment
plan calls for maintaining concentrations at 6-7ppb for 100 days. Gerry
believes today's booster should carry us to the end of the 100 day treatment
period. (The first treatment was 5/9 and 100 days later is 8/17. Based on this
year's history, concentrations should be roughly 7ppb on 8/17)
Gerry and I discussed the utility of doing a final dose should we still be
seeing new growth at the end of the 100 day period. We will review the state
of the Pond at that time.
Update 7/8/08
Today was the 2nd booster application (the original treatment was
5/9/08,
and the last booster was 6/5/08) - we are close to day 60 of the treatment.
During today's treatment ACT:
—Reapplied Sonar PR and Sonar Q pellets at the same locations as
previously
(the Mansion beach application emphasized left side (from the beach)
along Lakeshore Drive, where the surface infestation is worse).
—Raised the concentration of Sonar AS liquid from an average of 5.6ppb
(measured by the recent FasTEST) to a calculated 11ppb (the pellets
will contribute the last 1ppb).
ACT checked that at their 'deep-hole' spot, the thermocline is still at
about 14' (below which there is little fluridone mixing), and measured Secchi
depth at about 8'. Temperature and dissolved oxygen readings were taken at one
meter depths.
More from Mike Lowery: Today Gerry Smith and Michael Lennon of ACT and I did a visual inspection
of the coves and locations were plants with some healthy portions had been
spotted. We covered most of the shoreline, and it is much the same
everywhere: The milfoil is still putting out small (1-3") new 'puffs', but the
plants as a whole are rubbery - and mostly dying or dead.
This photo shows a full plant on the deck of the air boat, showing
these characteristics.
According to Gerry Smith, this is not uncommon and is referred to as
'poodling' - because like the tail of a poodle, it is hairless except for a few
puffs along the way. Gerry observed this has happened in prior treatments on
Dudley Pond. Gerry is confident that the treatment will be successful.
The underwater 'fields' of plants are still visible from the surface as
brownish, denuded plants with occasional green 'tufts' - the bulk of the plants
have not yet dropped.
Update 6/20/08
Water samples were taken on 6/12/08, one week after the "booster
treatment" of June 5th. The average concentration of the four
samples was 10.05 ppb. The plan is to do more sample testing near the end of
June, to determine the dose and timing of an second "booster" in July.
At present, there is still quite a lot of milfoil in
the Pond. The plants have stopped growing, and are mostly below the surface,
which would not have been the case without the treatment. The plants are not
healthy in appearance, and they should begin to fall over and drop out of the
water column within the next few weeks.
Update 6/2/08
A "booster treatment" of Sonar is scheduled for Thursday, June 5th, based on the
tests
of the water samples taken on May 21st. The following is from
ACT:
The results from samples collected on May 21st, some 12 days post-treatment from
our May 9th treatment date, average 7.35 ppb. Sonar has a reported half-life
in water of "roughly" three weeks, provided there's no water inflow or outflow
that would serve to dilute the concentrations further, in addition to Sonar's
normal breakdown from exposure to light. This average Fluridone concentration
of 7.35 ppb indicates that we were probably close to but a bit shy of our
targeted concentration goal of 12 ppb.
As with the first treatment, the pond will be closed on June 5th for all activity
(swimming, fishing, boating) for 24 hours. Normal activity can resume on Friday, June 6th.
Update 5/27/08
At this time, there is still a fairly large quantity of floating
milfoil fragments at the surface, along with some algae and floating tree
pollen. The effect of fluridone on milfoil is a slow process: It is expected
that the effects of the herbicide will begin to be apparent within the next few
weeks. At first, plant growth is slowed then stopped, then the plants become
further degraded until they ultimately die off.
Currently, the conditions are: